PROGRESS UPDATE - CP. CA MAU AQUATIC FEED FACTORY PROJECT

Friday 15-07-2022
The construction has started since the end of 2020. After the difficulties of the Covid epidemic, the CP. Ca Mau Aquatic Feed Factory project is gradually reaching the finish line and is expected to be transferred at the end of August 2022.

The project has a total investment value of nearly 75 million USD with a scale of 17.7 hectares. The factory will be used to produce and supply feed for shrimp and fish with a capacity of 124,800 tons/year.

CBC Construction Joint Stock Company has participated in the construction of the project with more than 40 different categories, the food production 10-floor tower is more than 50 meters high and the interior designs of the whole factory.